National Road Network Program Pilot Data Development and Conversion Services
October 7, 2026Originally constructed to meet 1970s Clean Water Act standards, the City of Pittsfield’s 17-million-gallon-per-day (MGD) wastewater treatment plant required significant upgrades to achieve increasingly stringent phosphorus and nitrogen limits in its National Pollutant Discharge Elimination System (NPDES) permit.
Aging Infrastructure and New Regulations
The City needed a reliable process to achieve a total effluent phosphorus concentration of 0.1 milligrams per liter under varying conditions. Aging equipment also had to be addressed to improve solids handling, treatment efficiency, and reliability. During construction, a new permit set an average total nitrogen limit of 709 pounds per day, requiring added improvements to the plant’s biological treatment and aeration systems.
The project required adding advanced nutrient removal to an operating facility without interrupting treatment. The plant was not designed for nutrient removal, and aging clarifiers, solids-processing equipment, and aeration components affected performance. Kleinfelder also responded to changing permit requirements and aeration limitations that pushed nitrogen above 7 milligrams per liter during summer peak demand.
Treatment Plant Upgrades
Kleinfelder evaluated treatment alternatives, life-cycle costs, and performance through process modeling, technology screening, and pilot testing. The team identified ballasted flocculation as the preferred tertiary treatment approach to treat phosphorous and supported vendor pre-selection. To advance nitrogen removal, Kleinfelder evaluated biological treatment alternatives and developed aeration-control upgrades incorporating dissolved oxygen sensors, automated air-distribution valves, most-open-valve controls, and ammonia-based aeration control capabilities.
Supporting improvements included secondary clarifier rehabilitation, conversion of existing tanks to support an anoxic activated sludge process, and upgrades to valves, flow meters, and return activated sludge piping. New rotary presses and rotary drum thickeners replaced aging sludge dewatering and thickening equipment to strengthen operational efficiency and system reliability.
Project Results
The completed phosphorus-removal upgrade improved process control, solids management, and treatment reliability while helping the city comply with stringent effluent requirements. The first round of improvements was completed in January 2023, and ongoing nitrogen-removal initiatives are expected to further reduce discharge to the Housatonic River and, ultimately, the Long Island Sound.
Project Details
Location:
Pittsfield, MA
Owner:
City of Pittsfield